Victoria’s energy storage deadlines rule out solar thermal, hydro

The Victorian government announced on March 14 a $20 million tender, to install up to 80MW of grid-scale energy storage by 2018.

It invited proposals from batteries, pumped hydro, compressed air, flywheel, and solar thermal technologies.

But its deadlines, of 30MW expected to be installed by next summer and 50MW by the following summer, are impossible for two of those technologies to meet.

Pumped hydro facilities take several years to build, because dams, tunnels and pipelines would need to be built.

Solar thermal technologies, such as solar towers, would also take at least two years to build.

This second round of energy tenders follows the closure of the La Trobe Valley’s Hazelwood coal-fired power plant.

Like the article? Subscribe to Green Left now! You can also like us on Facebook and follow us on Twitter.

If you like our work, become a supporter

Green Left is a vital social-change project and aims to make all content available online, without paywalls. With no corporate sponsors or advertising, we rely on support and donations from readers like you.

For just $5 per month get the Green Left digital edition in your inbox each week. For $10 per month get the above and the print edition delivered to your door. You can also add a donation to your support by choosing the solidarity option of $20 per month.

Freecall now on 1800 634 206 or follow the support link below to make a secure supporter payment or donation online.